
A Brief Sketch
of the
Williams County Courthouse
(Prepared by Richard L. Cooley & Kevin Maynard)
On March 10, 1888, the Ohio Senate passed a
resolution to allow the commissioners of Williams County to either "repair,
enlarge and improve the present (old) courthouse, or to erect a new courthouse
at the county seat of (Williams) county". The commissioners decided to tear
down the old courthouse and erect a new building on the same spot.
On May 1, 1888, the first bonds to finance the
construction of this new courthouse were sold. Within a month, the county
officers were settled into their new "temporary" quarters in the old
Mykrantz Academy at the southwest corner of Lynn and Mulberry streets, where the
Andres O'Neil and Lowe Insurance Agency building is today located. By the first
of July, the old courthouse was completely cleared away so that construction
could begin on the new building.
The architect for the present seat of justice was E.O.
Fallis of Toledo. The building's architectural style is that of modified French
Baroque, influenced by Romanesque Revival. The general contractor was the firm
of Malone Brothers & Earhart, also of Toledo.
The first foundation stone for the courthouse was laid
at 1:40 p.m., October 1, 1888, and the first brick was laid at 1:27 p.m. October
22, 1888. The cornerstone at the northeast corner of the building was laid on
April 30, 1889, the 100th anniversary of the inauguration of George Washington
as the first president of the United States.
It had been rumored for may years that quicksand lay
beneath the soil of the court park. However, during the excavation no quicksand
appeared; instead, workmen encountered clay that the local newspaper reported as
being "so hard as to almost defy a pick."
A disagreement arose over which color of brick mortar
to be used, red or white. This was settled by building sample walls using each
color mortar and inviting the public to choose between the two. Which color was
decided upon?
During the construction f the 160 foot high mammoth
building, only minor injuries and accidents occurred. This is quite a feat
considering the building was constructed by hand using rope, tackle and pulleys,
with up to 70 men working on the building at once.
The building cost roughly $185,000, including the
furniture purchased from Conant Brothers of Toledo. Most of the brick came from
Chicago and the Berea and Amherst stone was dressed on the courthouse site by
stonecutters brought in from Scotland. These stonecutters awed the local people
by working on narrow scaffolds 125 feet in the air, carving the stone work on
the tower. The marble for the floors, stairs and wainscoting came from Georgia.
The roof was originally of slate supported by steel beams. The pillars are made
of granite.
The material for the courthouse was brought in by
railroad and hauled to court park by horses. One team of horses weighing 2400
lbs. pulled a stone that weighted 12,700 pounds. The windows are made of quality
American plate glass with a specifically designed curve to allow more light into
the offices.
The tower is 26 feet square with the walls being 3 feet
thick. It required 35,500 brick to build each four-foot segment of the massive
tower. The original clock was a Seth Thomas, which cost $999.00 and was
purchased through Theo. Kampf, a Bryan jeweler. The clocks were replaced and
renovated in 1976, as a bi-centennial project, at a cost of $12,000. The bell
from the old courthouse was placed in the new courthouse tower for a short time.
The present bell, weighing 3000 lbs., was hung in January, 1891.
The courthouse officials first began using their rooms
in July 1891. The Auditor, Probate Judge, Treasurer, Clerk of Courts and
Recorder still occupy the original offices assigned to them.
At a cost of $1,500.00 a heating plant was constructed
on N. Lynn St. at the present location of the General Telephone Co. building and
a tunnel built from that site to the courthouse. Coal-fired boilers provided
steam heat that was supplemented by 15 grate fireplaces made at Marshall,
Michigan (now bricked in) and installed throughout the courthouse at a cost of
$1,150.00. In 1901, a coal-fired heating system was installed in the basement of
the courthouse and use of the heating plant and tunnel discontinued. Little, if
anything, remains of the heating tunnel today. The coal-fired system was later
replaced by the gas heating system still in use.
In 1957, half of the fourth floor was renovated for
use, and in 1961 the elevator was installed.
The courtroom vaguely resembles the original as
finished in 1891. Since that time the courtroom has experienced several major
renovations, including having the ceiling lowered to its present height.
In 1973, the Williams County courthouse was entered
into the National Registry of Historic Places.